EPIC for NGL-3 AGRU 1 & 2 Amine Regenerators and Associated Equipment Revamp Project at Mesaieed

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC13105400 -EPIC for NGL-3 AGRU 1 & 2 Amine Regenerators and Associated Equipment Revamp Project at Mesaieed.

  • Year : 2013 - 16
  • Type : Epic Projects
  • Project Details :

    Scope of Work consists of replacement of Acid gas removal unit which includes Amine Regeneration Columns, MDEA Regeneration Re-boilers, Rich/Lean MDEA Exchangers, Inlet Filters for NGL-3 Train 1 & 2. Complete integration of AGRU equipment are to be done during shutdown period.

    Amine Regenerators and Associated Equipment Revamp1Amine Regenerators and Associated Equipment Revamp2

EPIC for Automation Upgrade Project at Dukhan

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC12107300 – EPIC for Automation Upgrade at FMDS, FSDS, FNDS, FSP and NFIS Facilities at Dukhan.

  • Year : 2012 - 2015
  • Type : EPIC Project
  • Project Details :

    Scope of Work mainly consists of two parts:

     

    Part A: EPIC for Automation Upgrade at NFIS Facilities.

    Replacement of existing DCS with a new FF DCS, existing DCS field Instruments with new FF instruments, existing ESD and F&G systems with TUV Certified SIL-3 redundant systems and shall be integrated to new FF DCS.
    Replacement of existing ESD instruments with new SIL-2 Certified Instruments and existing F&G devices with latest HART based F&G devices.
    Replacement of existing third party PLC and Microprocessor based systems such as Water Mist System/Turbine Control System/Fuel Gas Water Heater Bath System/Instrument Air Compressor System and Flare Control Panels.
    Modification of existing 110V AC UPS feeders to cater new loads.

     

    Part B: EPIC for Automation Upgrade at FMDS, FSDS, FNDS & FSP Facilities. 

    Construction of New Blast Resistant Control Buildings (3No’s) ergonomically designed having Oval shape along with HVAC systems for each of them.
    Construction of New Substations (2No’s), DG buildings (2No’s), Blast Resistant Guard Houses (3No’s) and associated shaded Car Parking’s for the same.
    Installation of new Transformers, DG sets, UPS system, LV Switch Boards, Perimeter Lighting, Lightning and earthing protection systems for the above houses.
    Replacement of existing DCS with a new FF DCS, existing DCS field Instruments with new FF instruments, existing ESD and F&G systems with TUV Certified SIL-3 redundant systems and shall be integrated to new FF DCS.
    Replacement of existing Fire Water Pump (FWP) Control System at FMDS and integration to new FF DCS.
    Relocation of existing FWP Control Panel from existing control building to new control building in FSDS & FNDS and integration to new FF DCS.
    SCADA system replacement at FMDS, FNDS & FSDS and integration to new FF DCS.
    Replacement of Third party Panels such as Flare Control Panels, Tank Vapour Blower systems, Burner Hot Oil Panels, HIPPS, Instrument Air Compressor Panels and Dehydration Relay Panels.
    Installation of Building Management Systems, Data Network Systems, VOIP Telephone Systems, Security & Access Control System along with road blockers, boom barriers, ANPRs and turnstile gates for all FMDS, FNDS and FSDS.
    Installation of FO Cables (approx. 40kms) in the OFF PLOT areas.
    Re-location of PAGA system, CCTV HMI’s, TETRA Radio Base Station and video monitors from old control building to the new building for FMDS, FSDS & FNDS.

    Control Room Foundation 1Control Room Foundation 2

EPIC for injection of Khuff gas to Arab-D cap using north field injection station phase-1 in Dhukan Fields

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC12107800- EPIC for injection of khuff gas to arab-d cap using north field injection station –phase-1 in dhukan fields.

  • Year : 2012-15
  • Type : EPIC
  • Project Details :
    • Design, procure, install and commission 16” buried gas pipeline from WHTP-H and L to NFIS through the 10” manifold to be installed as part of this project. The 16” pipeline will be terminated at NFIS and tie-in to the existing 20” line (to Injection Compressor) near pig receiver area. The Pipeline shall have mobile skid mounted pig launching/receiving facilities. The approximate length of the pipeline is approximately 1.47 Kilometers.

Procurement, Construction, Installation & Commissioning for Produced Water Treatment & Crude Oil Desalting Project

Additional Info

  • Client Total E & P Qatar
  • Project Title

    1646000544 A New Desalter package consisting of below equipment to the existing process trains at Halul.

  • Year : 2013 - 15
  • Type : Construction Project
  • Project Details :

    A) PCIC to add a new desalter package consisting of below equipment to the existing process trains at Halul and tie-in the same to existing facilities to keep the salt content of the crude oil below 25 PTW and BS&W below 1%.

    • 1st stage: Desalter skid, Recycle pump Skid, Mixing valves skids, Deluge valve skids
    • 2nd stage, Desalter skid, Inter –stage heat exchanger skid, Chemical injection package skid Deluge valve skids

    B) PCIC to add a new produced water package consisting of below equipment to the existing produced water system at Halul to keep the oil in water below 40 ppm and tie-in the same to existing facilities 1st stage flash drum Water booster pumps Hydro-cyclone package, Compact flotation unit Residual oil transfer pumps Chemical injection package Deluge valve skid.

    C) Modification of existing process control system, Emergency shutdown system and integration.

    D) Modification of existing QP water disposal system and existing closed drain system to accommodate the new installations.

    Flash Drum Ready for LoadoutFlash Drum Transporting to Halul Island

EPIC for Integrated Oily Water / Sludge Handling System

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC11109100 - EPIC for integrated oily water / sludge handling system, new drain system, fire protection for crude oil manifold and pipeline replacement at Halul.

  • Contract Value: QR. 103 Million
  • Year : 2012 - 2015
  • Type : EPIC Project
  • Project Details :

    The Project scope of work is to Replacement of produced water line, MOL pipeline, Sludge mitigation and treatment by mixers, oily water drains on the Halul island to be connected to Drain vessels and pumping out, fire protection for the crude oil manifolds and Spill and foam containment in tank farm by providing concrete kerb walls.

Supply of Instrument Manpower on Long Term Hire Basis and on Call-off Basis

Additional Info

  • Client QAFCO
  • Project Title

    RFQ-319135 - Supply of instrument manpower on long term hire basis and on call-off basis

  • Contract Value: QR. 6 Million
  • Year : 2012 - 15
  • Type : Call Off Service
  • Project Details :

    Supply of instrument manpower on long term hire basis and on call-off basis - frame contract for 3 years + 2 years extension option.

EPIC of Upgradation of AC UPS Units in NGL3

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC12105200 – EPIC of Upgradation of AC UPS Units in NGL3 at Mesaieed.

  • Year : 2012 - 2015
  • Type : EPIC Project
  • Project Details :

    Scope of Work mainly consists of:

    Construction of 3 Nos. new buildings with Package Air Handling Units.
    Up-gradation of AC and DC UPS units and F&G systems.
    DCS and RTPIMS modifications.

Provision of Integrated Construction Services - CA-2183

Additional Info

  • Client Occidental Petroleum Of Qatar Ltd. (OXY)
  • Project Title

    CA-2183 - Provision of integrated construction services

  • Year : 2013-16
  • Type : Call Off Service
  • Project Details :

    This contract covers fabrication, inspection, painting, delivery, load out and sea fastening of piping, structural works and other miscellaneous items onshore.

    Offshore provision of equipment and manpower for Mechanical Construction, hook-up, E&I personnel for cabling, testing, loop checking etc., on the clients vessels and platforms..

    We have also deputed our Engineers and Draughtsman to the clients office to carryout planning, prepare job cards etc. as well as supplying material controllers and warehouse personnel to the clients stores and warehouses.

5 Years Contract for Supply of Skilled Manpower

Additional Info

  • Client QAPCO
  • Project Title

    CONTRACT NO. 112400572 - 5 years contract for supply of skilled manpower

  • Contract Value: QR. 7 Million
  • Year : 2012 - 17
  • Type : Call Off Service
  • Project Details :

    5 years contract for supply of skilled manpower (mechanical planners, welders, rotating technicians and helpers).

EPIC for Replacement of Flare Tip at NFA (PS4)

Additional Info

  • Client Qatar Petroleum
  • Project Title

    EPIC for Replacement of Flare Tip at NFA (PS4)

     

  • Year : 2013-14
  • Type : EPIC
  • Project Details :

    EPIC for Replacement of all the existing HP /LP/ atmospheric flare tips assembly, including the pilot gas tubes and nozzles, with new assembly constructed from type 310 stainless steel. Replacement of the existing Ignition Panel with a flame proof (suitable for Zone 1) and IP 66 certified high energy spark ignition panel and replacement of the existing 4 lines from Flare Tip igniter up to the nozzles of HP/LP/Atmospheric flare tip assembly. The lines are Purge Gas line (1”), Smoke suppression line (3”), Pilot Gas line (1½”) and Igniter Gas line (1½”).

Supply, Construction and Installation of 8 nos Elevators at QG2 Trains 4 & 5 and Associated Facilities.

Additional Info

  • Client Qatar Petroleum
  • Project Title

    Qatar Gas Operating Company Ltd (PS4)

     

  • Year : 2013-14
  • Type : EPIC
  • Project Details :

    The project scope involves the Procurement, Fabrication, Installation and Construction of 8 nos Elevators inside QG2 trains 4 and 5. The Elevators being free issued by Qatar Gas, all requirements to facilitate the elevator installation are under DOPET scope.The various works involved in the project are:

    • Civil works for Elevator foundations
    • Structural Works for the Landing Platforms of the Elevator at higher elevation.
    • Electrical cable Installations, Instrumentation and Wireless Transmitters

     

Shutdown Maintenance Works for NGL-1, NGL-2 & NGL-4 Plants

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC11105900 - Shutdown maintenance works for NGL-1, NGL-2 & NGL-4 plants.

  • Contract Value: QR. 101 Million
  • Year : 2011 - 14
  • Type : Shutdown Project
  • Project Details :

    3 phase shutdown maintenance works for NGL-1, NGL-2 & NGL-4 plants, gas operations, Mesaieed.

EPIC for Creation of Additional Slots Manifolds.

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC11109900 - EPIC for creation of additional slots manifolds at FMDS & KMDS in Dukhan.

  • Contract Value: QR. 16 Million
  • Year : 2012 - 13
  • Type : EPIC Project
  • Project Details :

    EPIC for creation of additional slots manifolds at Fahahil main degassing station (FMDS) and Khatiyah main degassing station (KMDS) in Dukhan.

EPIC for Pilot CNG Plant

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC 11109900 Var.1 - EPIC for pilot CNG plant

  • Contract Value: QR. 10 Million
  • Year : 2012
  • Type : EPIC Project
  • Project Details :

    The Project scope of work is to  install CNG Filling Station in New Industrial Area consisting of CNG package skid, Containerized Control/Switchgear Room, CNG Dispenser, Area Lighting, Ti-ins with WOQOD for CNG , Tie-ins with KAHRAMAA for water and Electricity etc.

     

    EPIC for Pilot CNG  Plant - Construction in ProgressEPIC for Pilot CNG Plant - Construction in Progress

EPIC for Replacement of Instrument Air Compressor

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC10108100 - EPIC for replacement of instrument air compressor at PS-2 & PS-3

  • Contract Value: QR. 37 Million
  • Year : 2011 - 13
  • Type : EPIC Project
  • Project Details :

    Design and Detailed Engineering, Procurement, Installation, Construction, Pre-commissioning, Commissioning and Testing works related to:

    • Verify FEED documents to this EPIC scope of work and prepare FEED verification report.
    • Replacement of 1” HP Instrument air Header with 2 Inch at PS2  at the following platform at PS2 (PS-2E/2G/2A/2C and the interconnecting piping within the bridge.
    • Replacement of 1” HP Instrument air Header with 2 Inch at PS3 at the following platform at PS3 (PS-3E/3G/3A/3C and the interconnecting piping within the bridge.
    • Installation of HP and LP air compressor at PS2 & PS3. Demolition of existing HP Compressor and Air Dryers and interconnecting piping at both PS-2E and PS-3E. LP Compressor K-4207 Replacement -  PS2LP Compressor K-4207 Replacement - PS2

Provision of Integrated Construction Services

Additional Info

  • Client Occidental Petroleum Of Qatar Ltd. (OXY)
  • Project Title

    CA-1906 - Provision of integrated construction services

  • Contract Value: QR. 120 Million
  • Year : 2009-12
  • Type : Call Off Service
  • Project Details :

    This contract was awarded on 1st January 2009 as a continuation of the previous contract after re-bidding. Contract covered material procurement if required, fabrication, inspection, painting, delivery, load out and sea fastening of piping as well as structural works and other miscellaneous items at onshore.

    At offshore provided manpower for Mechanical Construction, Hook-up, E&I personnel for cabling, testing, loop checking etc., up to Superintendent level.

    We have deputed our Engineers and Draughtsman to the clients office to carryout planning, prepare job cards etc. as well as Material Controllers, Warehouse Personnel to the clients various stores and warehouses.

EPIC for 8" NGL Line Topside and Riser Modification

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC10108600 - EPIC for 8" NGL line topside and riser modification at PS-2 & PS-3

  • Contract Value: QR. 6 Million
  • Year : 2011 - 12
  • Type : EPIC Project
  • Project Details :

    EPIC for 8" NGL line topside and riser modification at PS-2 & PS-3

Dolphin Tie-in to the Common Sulphur Project (CSP).

Additional Info

  • Client Dolphin Energy Ltd.
  • Project Title

    ITT-DC-ONS-266 - Dolphin tie-in to the common sulphur project(CSP).

  • Contract Value: QR. 65 Million
  • Year : 2010 - 12
  • Type : EPIC Project
  • Project Details :

    Major Scope Consist of Followings.

    • Review and Verify the Design Dossier for the Expansion Facilities and taking ownership of full responsibility for any errors and risk.
    • Construction scope consist of pipieline Crossings(Culvert 69 mtrs Long X 4.5 Mtrs Width X 5 Mtrs Deep) at Main Hamad Street  Including wih cordination RLIC, DOLPHIN and Other Third Party Agencies.
    • Laying of 6" Pipeline above ground on Sleepers 3 km Long and insulation, cathodic protection, gas detection devices etc.
    • Install Four (4) novated Molten Sulphur Transfer Pumps with all associated civil, piping, electrical & instrumentation works.
    • Supply and Install one (1) Eye Wash Station near the Tank Area including all earthwork operations and tie-in to existing potable water line.
    • Install one (1) novated SEEHT System (Skin Effect Electric Heat Trace System) with novated SEEHT piping on sleepers with all necessary accessories (valves, flanges etc).
    • Install one (1) novated Metering Skid, two (2) MOVs, six (6) Control Valves and sixteen (16) On/Off Valves on SEEHT pipelines.
    • Supply and Install all piping requirements for steam tracing of liquid sulphur tank and all interconnected steam traced pipelines.
    • Supply and Install all steam jacketed piping including steam traps and condensate recovery piping.
    • Supply and Install all Insulation and accessory.
    • Areva, France - PDCS – Modification works.
    • ABB, Malaysia – LV Distribution System – Modification works.
    • Honeywell - DCS/ICSS Modification works.
    • Supply, install and terminate new power, instrumentation and control cables.
    • Cathodic Protection Works.
    • Fire and Gas Detection Works including assistance from VESDA representative to supervise this work.

EPIC of Flexible Intermediate Wax Tank

Additional Info

  • Client ORYX-GTL
  • Project Title

    CN-057-10-EN - EPIC of flexible intermediate wax tank (MOC-415) at Ras Laffan

  • Contract Value: QR. 27 Million
  • Year : 2010 - 11
  • Type : EPIC Project
  • Project Details :

    Review and verify FEED documents, Process deliverables, Civil/ structural deliverables, Mechanical/ Piping/ Tanks deliverables, Electrical deliverables, Instrumentation/ DCS, configuration deliverables, Loss prevention (F&G detection/ suppression) deliverables, Demolition works deliverables.

    Ware house spare pump – 01 Nos (Pompe Gabbioneta), Piping materials, Control Valve- 03 Nos, Shut down valve – 01no, Pressure Relief valve – 01 no, Vacuum Relief valve – 01 no, Loss prevention items, Instrumentation cables, Power cables for lighting.

    Extension of dike wall, Tank foundation, Demolition of existing Road, Construction of new asphalt road.

    Construction of Tank, Diameter = 25 meter and height = 15 meter, Piping prefabrication = 6,280 Inch Dia Approx, Site welding = 2,690 Inch Dia Approximately.

    Installation of field instruments, DCS/ SIS configuration works (Invensys), Cabling.

    Relocation of flood lighting, New street lighting, Cabling for street lighting.

    Installation of fire detectors on the tank, Relocation of fire hydrants, hose reels, Installation of new 3 fire monitors, Installation of new 4” deluge valve skid.

EPIC for Crude Oil Import Export Facilities Upgrade Project

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GT07101900 - EPIC for crude oil import export facilities upgrade and beach landing valves at Halul

  • Contract Value: QR. 228 Million
  • Year : 2008 - 11
  • Type : EPIC Project
  • Project Details :

    Design and detailed engineering, procurement, installation, construction, pre-commissioning, commissioning and testing works related to crude oil import export facilities upgrade and beach landing valves at Halul.

    Major Scope Related to:

    Main Crude oil Import Export Pumps(4 Nos.) from Flow serve or Clyde Pumps (3.8 MW Motors).

    MOVs -49 Nos from 16” to 48” x 150# for Various Manifolds.

    Remote Operated Beach landing valves (ROVs).

    Cooling Water System along with individual PLC or with Controller.

    Suction Strainers 36” for Pump. 2.6 Auto Circulation Valves (ARC), Overhead Crane.

    EVSD System, Drive management System (DMS).

    11KV Switch boards and Distribution Transformers.

    LV Switch Boards.

    F&G Equipments or Instruments.

    Control valves.

    Process instruments.

EPIC for 16ӯ JET A1 Pipeline from BSV3 to NDIA

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GT09106100 - EPIC for 16ӯ JET A1 pipeline from BSV3 to NDIA

  • Contract Value: QR. 69 Million
  • Year : 2010 - 11
  • Type : EPIC Project
  • Project Details :

    Design and Detailed Engineering, Procurement, Installation, Construction, Pre-commissioning, Commissioning and Testing works related to:

    Verify FEED documents to this EPIC scope of work and prepare FEED verification report.

    PROCUREMENT(Major)

    Pig Receiver.
    Control Valve, ESD Valve & MOV.
    Custody Transfer Metering System.
    LV Switch board.
    Fiber Optic cable.
    Cathodic Protection –Cable anodes & Transformer Rectifier Units
    110 V UPS.
    Pre-filter and Filter Coalescer
    CONSTRUCTION (Major)
    PIPELINE
    Laying of 16.8 km of the pipeline for BSV-3 TO NDIA Through corridor.
    Stringing and bending work.
    Welding  and carrying out tie in joints.
    Hydro testing, drying & Nitrogen purging of the pipeline.
    Carrying out base line survey for the pipeline.

    PIPING

    Fabrication & installation of the  station piping including valves & MOV.
    Installation of Sump Tank, Filter Coalscers, Pig Receiver & Metering Skid at NDIA.

    CIVIL

    Preparation of ROW along the pipeline.
    Carrying out trenching work for laying of  pipeline(16.8km).
    Construction of SER building at NDIA.
    Carrying out Micro tunneling or HDD (1 No).

    INSTRUMENTATION

    DCS modification at Refinery.
    Provision of new RTU at BSV-3.
    Provision of New dedicated standalone Fire safe controller at SER for the ESD and F&G Systems.
    Provision of Custody Transfer metering system (By EMERSON or approved equal) at NDIA.
    Provision of Leak Detection system

    PR-ECOMMISSIONING AND COMMISSIONING WORKS

    Pre-commissioning & Commissioning

EPIC of LPG Hydrogenation Facility at ORYX-GTL Plant at RasLaffan

Additional Info

  • Client ORYX-GTL
  • Project Title

    EN-1218 - EPIC of LPG hydrogenation facility at ORYX-GTL plant at RasLaffan

  • Contract Value: QR. 42 Million
  • Year : 2009 - 10
  • Type : EPIC Project
  • Project Details :

    Engineering, Procurement, Delivery, Fabrication, Testing, Installation, Pre-Commissioning and Commissioning of LPG Hydrogenator Facility at Ras Laffan consisting of following major items:

    LPG Hydrogenator (Reactor),
    Column (Separator),
    Feed Pumps,
    LPG Recycle Pumps,
    Reflux Pumps,
    Hydrogenated LPG Product Pumps,
    Recycle Gas Compressor,
    Electrical Heater,
    LPG Recycle Cooler,
    Stripper Condenser,
    Stripper Reboiler,
    LPG Product Cooler,
    Condensate Pot,
    Pipes, Fittings, Valves, Flanges, Studs, Bolts, Nuts, gaskets, clamps, anchors, sleeves, packers etc,
    Painting and Insulation,
    Electrical Items,
    Instrumentation and Control Items,
    Fire & Gas Items,
    Provision of First Load of Catalyst, All Civil and Structural Works,
    Fire Proofing Works.

EPIC of New Lifeboats & Replacement of Existing Lifeboats at PS-2/3/4

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC09110600 - EPIC of new lifeboats & replacement of existing lifeboats at PS-2/3 & NFA (PS-4)

  • Contract Value: QR. 17 Million
  • Year : 2010 - 12
  • Type : EPIC Project
  • Project Details :

    Endorse FEED package and Detailed Design.

    Procurement

    Heat Shield Panels –PS3 (140 sq m), BA Cascade System-4 nos. PS3  Life Jacket Cabinet.

    Structural steel for Deck extension and modification – 87 Tons.

    Platform works cover structural deck extension, provision of new BA cascade system and safety equipment, associated electrical & instrumentation works DCS modifications vendor – Yokogawa; ESD & FGS - Invensys

    Lifeboat Works.

    PS-2Q – Installation of 45 man Lifeboat (relocated from PS-3Q).

    PS-2E – Demolition of existing 36 man Lifeboat and replace with 45 man Lifeboat (relocated from PS-3Q).

    PS-3Q (East) – Installation of new 60 man Lifeboat.

    PS-3Q (North & West) – Removal of 3 existing 45 man Lifeboats and replace with 3 new 60 man Lifeboats.

    PS-3F – Demolition of existing 36 man Lifeboat and replace with 45 man Lifeboat (relocated from PS-3Q).

    PS-3E – Demolish existing 36 man Lifeboat.

    NFA – Install 50 man Lifeboats (5 Nos.).

    Carry out Performance Test / Site Acceptance Test (SAT).

Maintenance Support Services for NFA Major Shutdown - 2009

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC09105100 - Maintenance support services for NFA major shutdown in 2009

  • Contract Value: QR. 14 Million
  • Year : 2010
  • Type : Shutdown Project
  • Project Details :

    Maintenance support services for NFA major shutdown in 2009

Turnaround Shutdown for Crude Refinery 1 & 2 and Condensate Refinery Utilities

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC081083A0 - Turnaround shutdown for crude refinery 1 & 2 and condensate refinery utilities in 2009, Mesaieed

  • Contract Value: QR. 68 Million
  • Year : 2009
  • Type : Shutdown Project
  • Project Details :

    Overhaul of about 600 equipment includes exchangers, air coolers, compressors, vessels, columns, reactors, regenerator, boilers, tanks. Incorporation of Plant change requests (PCR’s) both Mechanical & instrumentation, inspection advice tickets for repairs and mobilization of specialized vendors for various equipments like pumps, compressors, relay panels. Procurement of material for PCR’s.


    Work force involved was around 1200 personnel including all the sub contractors like Scaffolding, Insulation, Refractory, Painting, NDT, Heat Treatment, Motors overhaul, Valves overhaul. Main equipment mobilized are Mobile Cranes, High pressure Water jetting. Pumps and number off other equipments & vehicles required for completion of Shutdown in a planned manner.

EPIC for New LPG Bottling Plant for WOQOD at New Doha Industrial Area

Additional Info

  • Client WOQOD / Qatar Petroleum
  • Project Title

    GTC 05/115/ED - EPIC for new LPG bottling plant for WOQOD at new Doha industrial area - Doha.

  • Contract Value: QR. 173 Million
  • Year : 2007 - 09
  • Type : EPIC Project
  • Project Details :

    Engineering, procurement, installation, construction and commissioning of new LPG bottling plant for WOQOD at new Doha industrial area – Doha.

    Fabrication, transportation and erection of 3 nos. LPG bullets of approximately size 4.9mtr. ID x 30mtr. long (116 Ton each).
    Site fabrication of 1 no. fire water tank of size 10mtr. dia x 10mtr. height (40 Ton)
    Shop fabrication and site installation of pipe rack (30 Ton), fire water pump house & piping.
    12 kg filling plant & cylinder maintenance hall equipment.
    Fire water pumps – 3 nos.
    Loading arms & weighing bridge – 2 nos each.
    LPG pumps – 2 No.
    LPG compressor – no.
    Instrument air compressor & dryer package – 2 no.
    PCMS/ESD/F&G/System.
    HV panel/415V panel/MCC & transformers.
    Construction of buildings / structural – control room, 12 Kg filling hall,  maintenance hall, loading gantry, 11KV sub-stations (2 Nos.) etc.
    Construction of LPG bullet foundations & fire water tank foundation.
    Area leveling, construction of roads, fencing, area lighting, green belt etc.
    Structural fabrication approximately 60 Ton and piping work approximately 4200 Inch dia.

EPIC of LPG Pumping Stations and Associated Facilities

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GTC 05/115/ED - WCR NO. 7 (VTC NO.3) - EPIC of LPG pumping stations and associated facilities.

  • Contract Value: QR. 74 Million
  • Year : 2007 - 08
  • Type : EPIC Project
  • Project Details :

    Design and detailed engineering, procurement, installation, construction, pre-commissioning, commissioning and testing works related to LPG pumping stations and associated facilities and commissioning of 6", 42 km of pipeline.

Installation of CEMS Nozzles and Associated Structures.

Additional Info

  • Client Qatar Petroleum
  • Project Title

    LT11104400 - Installation of CEMS nozzles and associated structures at RG plant Dukhan

  • Contract Value: QR. 4 Million
  • Year : 2011 - 12
  • Type : EPIC Project
  • Project Details :

    Installation of cems nozzles and associated structures at RG plant Dukhan.

Turnaround Shutdown in 2009 at QP Rrefinery, Mesaieed

Additional Info

  • Client Qatar Petroleum
  • Project Title

    GC081083B0 - Turnaround shutdown in 2009 at QP refinery, Mesaieed

  • Contract Value: QR. 130 Million
  • Year : 2009
  • Type : Shutdown Project
  • Project Details :

    Overhaul of nearly 1000 equipments includes exchangers, air coolers, compressors, vessels, columns, reactors, regenerator, boilers, tanks.

    Incorporation of plant change requests (PCR’s) both mechanical & instrumentation, inspection advice tickets for repairs and mobilization of specialized vendors for various equipments like pumps, compressors, relay panels. Procurement of material for PCR’s.

    Work force involved was around 1800 personnel including all the sub contractors like Scaffolding, Insulation, Refractory, Painting, NDT, Heat Treatment, Motors overhaul, Valves overhaul.

    Main equipment mobilized are Mobile Cranes, High pressure Water jetting. Pumps and number of other equipments & vehicles required for completion of Shutdown in a planned manner.
    Equipment Inspection & Repair works (Exchanger, Aircooler, Column, Vessels, Reactor, Heaters)
    Removal & Installation of Safety relief valves, control valves and deliver & collect at workshop for overhaul.
    Removal & Installation of Electrical motors and deliver & collect at contractor workshop for overhaul.
    Inspection of Exchanger Tubes.
    Piping and Equipment Insulations.
    Piping and Equipment (Coating / Painting).
    Scaffolding for inspection holes, relays inspection and service done by vendors.

Fabrication and Offshore Hook-up

Additional Info

  • Client Occidental Petroleum Of Qatar Ltd. (OXY)
  • Project Title

    CA 1583 - Fabrication and offshore hook-up.

  • Contract Value: QR. 250 Million
  • Year : 2004-08
  • Type : Call Off Service
  • Project Details :

    This contract was awarded on 1st January 2004 as a continuation of the previous contract after re-bidding. Contract covers material procurement if required, fabrication, inspection, painting, delivery, load out and sea fastening of piping as well as structural works and other miscellaneous items at onshore.

     

    At offshore provide manpower for Mechanical Construction, hook-up, E&I personnel for cabling, testing, loop checking etc., up to Superintendent level.

     

    We have deputed our Engineers and Draughtsmen to the clients office to carryout planning, prepare job cards etc. as well as Material Controllers, warehouse personnel etc. to the clients various stores and warehouses.